Project Overview

Modernizing a 12-Story Midtown Office

This Class-B mid-rise office tower on Peachtree Street had a 20-year-old mechanically attached TPO roof that was leaking at penetrations and an original EIFS façade that was chalking, cracking at control joints, and spotting with efflorescence. The owner wanted to extend the building's useful life by another 20 years and reposition it in the Midtown leasing market.

Our scope covered a complete TPO tear-off and replacement, tapered insulation to correct longstanding ponding, elastomeric façade coating with full crack repair, and rooftop-equipment curb and flashing replacement. All work was performed with the building 94% occupied and the ground-floor retail open daily.

Client Type

Commercial property owner

Location

Midtown, Atlanta GA

Timeline

28 weeks, 6 phases

Occupancy

Full tenant operations maintained throughout

Midtown office tower
Project Photos

The Work in Three Phases

Existing Conditions

Existing conditions

Roof Replacement

Roof replacement

Completed Exterior

Completed
Detailed Scope

Systems, Materials & Logistics

TPO Roof Replacement
  • Full tear-off of 32,000 sq ft 60 mil TPO and saturated insulation
  • Tapered polyiso to R-30, eliminating 14 historic ponding zones
  • 80 mil reinforced TPO designed for long service life
  • All rooftop equipment curbs, penetrations, and scuppers replaced
Façade Coating System
  • Pressure-wash and full surface prep across all four elevations
  • All control-joint sealant cut out and replaced with low-mod urethane
  • Reinforced elastomeric base coat + high-build finish coat
  • Manufacturer-warranted coating system for waterproofing and color stability (term varies by product tier)
Rooftop Equipment & Safety
  • All RTU curbs re-flashed; no unit offline more than 4 hours
  • OSHA-compliant perimeter warning line and fall-arrest tie-offs
  • New permanent roof-hatch walk pad and service pathways
Occupied-Site Logistics
  • All loud demo work performed between 6 PM and 6 AM
  • Swing-stage scaffold rotated face-by-face to maintain tenant light
  • Ground-floor retail entrances kept open with overhead protection
  • Weekly tenant newsletter and monthly ownership progress report

"Doing a full envelope on a 12-story occupied building usually means complaints. We had two. Both were resolved the same day. The roof warranty alone saved us underwriting-wise, and the refreshed façade has already helped us bring rents up by 8%."

Commercial Property Owner

Midtown, Atlanta GA

Related Services

Services Used on This Project

Planning a Commercial Roof or Façade Project?

Our Atlanta commercial division handles fully occupied, multi-phase exterior work with zero-tenant-downtime experience. Schedule a walkthrough.